Impact Site
Road structure, curbs, sidewalks and asphalt
09/24/2026: The corresponding road and pedestrian structure (sidewalks) has been completed, to date, over a length of approximately 175 linear meters. The layers of the road structure were executed successively, up to the asphalt concrete wearing course, with each stage being accompanied by checks and tests confirming compliance with the quality requirements set out in the project. Also during this period, the sidewalks corresponding to the executed road structure were built on both sides of it. The curbs were installed and the two foundation layers were executed, up to the asphalt concrete wearing course.